Closed
Bug 716730
Opened 12 years ago
Closed 12 years ago
spec and purchase 10gb cards for bm-vmware*
Categories
(mozilla.org Graveyard :: Server Operations, task)
mozilla.org Graveyard
Server Operations
Tracking
(Not tracked)
RESOLVED
WONTFIX
People
(Reporter: dustin, Unassigned)
References
Details
As part of the scl3 move, we will be building new VMs on the generic vmware cluster in scl3, then moving the existing bm-vmware* (except bm-vmware03, which is too old to move), and migrating the instances back to bm-vmware*. As part of this process, we should put 10gb cards in bm-vmware*. Soo, let's get that hardware specc'd and ordered and shipped to scl3 so we can get it installed when the time comes.
Comment 1•12 years ago
|
||
Is there really value in retrofitting these DL385s for this vs. buying new ESX hosts? Bug 716710 is that.
Status: NEW → RESOLVED
Closed: 12 years ago
Resolution: --- → WONTFIX
Reporter | ||
Comment 2•12 years ago
|
||
First, these are BL460c's. Second, these will be a fairly temporary solution in scl3 -- we are leaning toward replacing all vmware build capacity with physical hardware. So usage plans are actually well-aligned with the expected lifetime of this hardware. For record, the move plan is build new VMs in scl3 on the generic VMWare infrastructure (bug 716710) transition those into production shut down the VMs in sjc1 bring the nodes in sjc1 (bm-vmware*) to scl3 (all but 1 old unit) add 10gb cards (this bug) move VMs back to those nodes this plan keeps releng's fairly heavy builder footprint (~100 instances, and we'll be looking for a lot more disk space each) off of the generic ESX cluster in the long term.
Status: RESOLVED → REOPENED
Resolution: WONTFIX → ---
Reporter | ||
Comment 3•12 years ago
|
||
:lerxst, it looks like it's not economical to put 10gb on these BL460's. That leaves a few options: 1 buy new hardware for releng's use (temporary) 2 move the BL460's as-is, without 10gb 3 run releng on the generic infra for longer than the duration of the move (which will probably require more hardware) what do you think is the best course? Will IO for 2 be slower than the current arrangement?
Comment 4•12 years ago
|
||
Is the long term releng plan to vacate ESX? I'm fine buying new hardware here if it makes sense.
Reporter | ||
Comment 5•12 years ago
|
||
Yes - the plan of record is to build out DL120G7's as linux builders and stop using vmware. That will not happen until some time after the scl3 move is complete, though. I'm open to revisiting that plan, but I do not want to do so in the context of the scl3 move.
Comment 6•12 years ago
|
||
Sounds good, shall we close this as WONTFIX for now and revisit after scl3?
Reporter | ||
Comment 7•12 years ago
|
||
indeed.
Status: REOPENED → RESOLVED
Closed: 12 years ago → 12 years ago
Resolution: --- → WONTFIX
Updated•9 years ago
|
Product: mozilla.org → mozilla.org Graveyard